How to Update Milestones from a Smart Form

Record milestone values while completing a form.

Overview

A Milestone question links a form answer to a field on a project milestone. For example, an end-of-job form can record the completion date, job status and description of work completed.

Each question updates one field. Use separate questions to capture several values against the same milestone.

Before You Start

Add the milestone to each project where the form will be used. Configure any status options or remarks dropdown choices before linking the questions.

Adding a Milestone Question

  1. Go to Main Menu → Forms, then click Form Templates at the top right of the page.
  2. Open the form and click Edit.
  3. Select a section and click Add question, or select an existing question.
  4. Open the Question tab and set Type to Milestone.
  5. In Question text, enter the question, such as Date work completed.
  6. In Milestone, select the milestone you want to update.
  7. In Field, select where the answer should be recorded.
  8. Click Save.

Choosing the Field

The available fields depend on the milestone’s configuration:

  • Actual — Record an actual value, such as the completion date.
  • Forecast — Record a planned value, such as the expected completion date.
  • Option — Choose from the milestone’s configured status options.
  • Remarks — Enter text or select a configured remarks dropdown choice.

Option and remarks fields may appear under your company’s own column names, such as Site Status or Works Completed.

The Allow user to add additional free-text remarks setting is separate. To link a question to the milestone’s Remarks field, select that field in Field.

Example: An End-of-Job Form

For three questions linked to the same build milestone:

  • Job status → its status option field.
  • Description of works completed → its remarks field.
  • Date completed → Actual.

Submitting the Form

The milestone is updated when the form is submitted. The recorded values can be viewed on the site’s Project Milestones tab.

If the form reports that the milestone is unavailable on the project, the linked milestone must be added to that project.

If the Milestone Is Not Editable

Review Who's Responsible For at both the milestone and project levels:

  1. Open the milestone for editing.
  2. On the first page, review Who's Responsible For to see which roles have permission to edit it.
  3. Open the relevant project, click Edit and scroll down to the Project milestones section.
  4. Find the milestone and review its Who's Responsible For permissions for that project.

Next Steps