How to Change the Order of Custom Milestones on a Project
Arrange a project's custom milestones in the order you need.
Changing the Order
- Go to Main Menu → Projects.
- Click the pencil icon to edit the project.
- Scroll down to Project milestones and select Custom Milestones.
- Drag the milestones into the required order using the move icon on the left of each row.
- Click Save order.
XMP displays Successfully saved milestone order when the change has saved.
Which Milestones Can Be Reordered?
The Custom Milestones tab contains milestones created specifically for that project.
The Milestones tab contains milestones linked from the main milestone list. It does not have the same drag-and-drop or Save order controls.